BSP Fit for future Awards CWDP01

Personal Goal

Date from:

April 10, 2021

Date to:

April 10, 2021

BSP Fit for future Awards CWDP01

  • BSP Fit for the Future: Success story this week
  • Initiative Title: Saving a shutdown of CWDP01
  • Congratulations to the Integrated Team for Taking Accountability & Challenging the Status Quo!! Delivering Fit for the Future

 

What was the opportunity?

CWDPO1 is East Asset’s crown jewel, together with BLWJ01 producing about of oil m3 ofgas every day.

In BP20, we had scheduled 3 shutdowns of 1 week each for this platform for 2021 to accommodate:

  1. Dropping spools for SRL change out
  2. Reinstating spools after SRL change out + CW52 spool reinstatement
  3. CW41 X-mas tree change out

 

What was the outcome? What can we learn from this story?

  1. With great teamwork and a lot of can-do attitude, we were able to cut one 7-day shutdown of CWDPO1 from the plan.
  2. This means that East will produce a total of this year.
  3. For BLNG this means that there is an opportunity for one extra cargo in April 2021 with the surplus gas.

 

What did we do?

  1. Going ahead with the plan would have meant that we are losing about of gas.
  2. The Team Was Not Satisfied Challenge the Plan to Improve With This and Worked on a Better Solution
  3. Due to a cross-team collaboration, a similar X- mas tree as CW41 could be secured and can be installed in one of the 2 shutdowns
  4. The team also managed to increase the scope in the first SD.
  5. With further optimization and 24hr support of resources and vessel, close communication with TWC, the integration team and engaging the execution party 6 months in advance, the team was confident to cut one shutdown.